A new hotel wing rarely opens all at once. The spa needs to be ready for one date, the bedrooms for another, and the decorating has to keep pace with both.
Aldwark Manor has added an extension to the back of the hotel, and the main contractor brought us in to deliver the decorating package. That covers the new en suite bedrooms, finished to the standard Aldwark's guests expect, the corridors, staircases, staff and back-of-house areas, and downstairs, the meeting rooms and the spa.
The new space is opening in phases, with the spa first and the bedrooms following, and each phase has a fixed date that doesn't move. The work couldn't run at one steady pace, so the labour on site had to follow the programme.
The extension also has a lot of new oak, including the staircases, which needed a flame-retardant finish that still looked right in a hotel of this standard.
Decorating package for a new hotel extension: en suite bedrooms, corridors, staircases, back-of-house areas, meeting rooms and the spa.

One contracts manager on the job from day one. The main contractor always deals with the same person, so dates, changes and priorities don't get lost between visits.
Labour scaled to the programme. When the spa had to be ready for its opening date, we put extra decorators on to get it finished, then moved the focus back to the bedrooms. Dates are agreed with the main contractor early and we plan the labour back from them.
Spray-applied mist and first coats. On the new bare surfaces, we sprayed the mist coat and first coat throughout to cut the time needed before the finishing coats could go on.
Flame-retardant finish on all the oak. Every piece of new oak, staircases included, was stained with Morrells and finished with Thermoguard flame-retardant varnish, giving the timber a fire barrier without changing its look.
The spa is finished, and work on the bedrooms and remaining areas is continuing to the hotel's programme. We'll add photos of the finished bedrooms here once they're handed over.

Hotel openings run to dates set well before the decorators arrive, and on this job the labour has moved with every one of them.
Hotels set the dates and the decorating fits around them, whether it's a new extension or a live building that never closes. We've delivered a year-long phased programme at DoubleTree by Hilton Leeds City Centre and phased redecoration of 99 bedrooms across Village Hotels Leeds North and Wirral.
You can read more about how we work with hotels and about our commercial painting work.
Planning a hotel extension or a phased opening? Call us on 01924 723723, email enquiries@gmegroup.co.uk or get in touch here and we'll get back to you.


















Aldwark Manor: decorating a new hotel extension, one phase at a time

Decorating a new hotel extension at Aldwark Manor, from the spa to the en suite bedrooms, one phase at a time.
Askham Bryan College

Redecorating student accommodation, covering 63 bedrooms, kitchens and corridors, delivered to a high-quality finish with real-condition results.
Bannatyne Health Clubs

National refresh of health club interiors and exteriors, completed out-of-hours with zero disruption to members.
Bradford student accommodation

Using a phased approach on the full redecoration of a 40-bedroom student block - to a tight programme.
Carlton Academy

Stripping back varnish entirely and redecorating a school from scratch, during half-term.
Chocolate Works & LiLAC - Care Home Decorating

Two care home decorating programmes - 42 bedrooms at a listed York landmark and 12 years of maintenance across 11 LiLAC sites in Leeds.
Doncaster Royal Infirmary

Enhancing clinical environments across a busy NHS hospital with vibrant, safe finishes and minimal disruption.
DoubleTree by Hilton Hotel Leeds City Centre
.jpg)
Year-long phased decoration programme across a full-service city-centre hotel.
Harrogate Convention Centre car park: brighter, safer and easier to drive

A brighter, safer car park at Harrogate Convention Centre, painted for North Yorkshire Council under our framework.
Health Clinic Wakefield

Delivering sensitive refurbishment at a five-storey community clinic while supporting day-to-day operations.
iQ Huddersfield
.jpeg)
350-bedroom student accommodation redecoration in a six-week summer window.
Kirk Balk Academy

Consistently delivering a long-term decorating contract across an 11-school estate.
Leeds General Infirmary - NHS Hospital Decorating Programme

A circa 10-year decorating and refurbishment programme across the older parts of Leeds General Infirmary, delivered around a live hospital.
New Lodge Housing Estate

Improving 250 council homes for Berneslai Homes with coordinated redecoration and tenant-first delivery.
Springwell School

We developed a decorating specification that balanced the right aesthetic with the practical resilience the setting required.
The Green, University of Bradford

Seventy-five bedrooms delivered in two-and-a-half weeks against a three-week deadline.
Ulster Yarns

Refurbishing a 3,600 sq ft factory with specialist coatings and minimal disruption to ongoing textile operations.
University of Huddersfield

Transforming learning and heritage spaces across a major university campus with smart, coordinated delivery.
Village Hotels - Leeds North and Wirral

Phased redecoration of 99 bedrooms and communal areas across two sites,

Flexible commercial finance for your project, with fast decisions and expert support.
Mr Samuel David Peel, trading as CP Business Finance (FRN: 1034961), is an appointed representative of White Rose Finance Group Limited (FRN: 630772), which is directly authorised and regulated by the Financial Conduct Authority. CP Business Finance acts as a credit broker, not a lender. Please consider borrowing decisions carefully — property or other assets offered as security may be at risk if you cannot keep up with repayments.